Carbon Fiber Project Construction Hits the "Fast-Forward Button"

Recently, at the construction site of Oriental Energy (Maoming) Carbon Fiber Co., Ltd, a bustling scene of intense activity has unfolded, with all tasks advancing in an orderly manner as the team makes an all-out push to meet the project's construction goals.

So far, the project has completed the structural topping-out of the central control room and the 35KV substation. The carbonization workshop, slated to be the first to commence operations, has finished its steel structure installation, with 80% of the roofing and wall cladding completed. The spinning workshop, raw silk temporary storage warehouse, and carbon fiber temporary storage warehouse have all completed foundation work and are now undergoing steel structure assembly. In the coming spring, the construction team will accelerate progress on the civil engineering aspects to allow ample time for subsequent equipment installation and debugging, striving to achieve completion and operational status by October.